Back to commenting on the contractors efforts, I’d have to say that he is professional in every manner. His construction practices seem to be in line with what I know to be good and parallel with recommendations made by others I know in the construction industry. Anyway, after the ground breaking ceremony and the following days through 24 January 2008, progress was made with building the cinder block framing and placement of crushed stone in the bottom of each hole where the columns were to be, construction of the rebar columns was completed and were placed in the pre dug holes and concreted in place, wood forms for placement around the rebar the were made, and the dirt was replaced and compacted.
![]()
So, that is where we currently stand. Periodic progress updates to be provided.