they have done the scaffold,and starting outside with some work too.....

we went to Korat PD office at the 23.5.16 to choose the tiles,Laminate and made some more changes which affected the finish time for the house.

i completely forgot to tell that we made the first change early 2016,because i was not happy with the small doors for my electrical in the original plans.

the 2.change was at the 18.3.16.....before the roof came....in the contract they have 3 inch roof insulation.....i wanted 6 inch roof insulation on the ceilings....
plenty of time for them to change it without any hassle.....well....

it ended,that we had to go to homepro and buy the 6 inch insulation...after several phone calls........

they gonna pay us back,take it off from our last payment.

so while we were in the office,i asked what kind of toilet fans they put in.....
showed us these ugly ones for the walls,with shudders on the outside.....
on heavy rain,its gonna rain in and big bugs can walk in as they want......changed to a ceiling fan with duct to the outside.....

and some paint for the interior i changed too,from "Supershield Duraclean" to a"A+"


a change in the original contract means they get 1 month more finishing time before penalties for them apply(500Bht a day)for each change...

so with us there are 3 months on top off the original timeframe....which is due at the end of february 2017......its gonna be May 2017

.....its not gonna happen anyway......





some small stuff......




..fair a bit to fill up here....thanks that i dont have to pay for extra rendering materials.....