Hi Lom
Great pictures and great thread. I just have one thing to mention:

Quote Originally Posted by Loombucket View Post
Quote Originally Posted by Archer
How many days was this wall building projected to last? (ie how many days are you behind schedule?)
The job was supposed to take fourty days. That included all the walls to 'being painted' standard, steps down to the rear archway and a runner beam for the gate. We have, so far, lost four full days, due to 'other work' and one whole and two half days due to rain. Not the end of the world and about the same as we lost during the start of the house build.
Are the wall finished after Day Seventy Six or will the (never ending) story continue. I am amazed that they can be so far behind. But TiT.

I'm not sure that I will show this thread to Mrs. Archer because I'm sure she would want a wall like this around our land.

Cheers
/Archer