We've gone three days without a sign. A? tells me that it is not a problem, as he is sure that we can finish on time. He forgets to tell me that they are doing another two jobs, for richer people, at the same time as ours. I keep quiet.
Anyway, The team rip the covers off the mid-beam section and Sing carries on with the all important rod tweaking.
Somchai gets started on the, already, dwindling pile of blocks,
...and the new boy, Goon, starts repairing the hose pipe with bits of old motorcy inner tube.
God poses for his mugshot (his mrs was delighted),
...before making his way down to the last beam assembly point.
Nuy is busy cuttin blocks down, to make up the thickness of the mid beam.
Somchai quickly puts them in a safe place.
Having tweaked his rods, Sing starts cleaning up the pillar stubs at the back of the high wall. He dresses the tops with a bit of pug, so that the top beam framework will sit nicely in position.
Back on the beam, the channel has made it to the other side of the drive,
...the last section is just about ready,
....but it looks like rain, a lot, is nearly here.
We make it to the last turn before the wind starts blowing.
![]()