Quote:
Originally Posted by Thai Dhupp
What else can we do?! The supply is the supply... I will try to secure the biggest available which fits my future needs (stage 1, 2 and 3 of the build, plus out door requirements, and pool) but even supposing i got 100% of what i want, if more houses are built later can't the power company just 'cut mine back' to allow those late arrivals a dribble of power or... do i secure my requirements first 'n they can make do with solar only, or a campfire n flaming torches (and a pedal driven TV).
Lol it won't matter what size "supply" you get (meter) because that isn't your "power limit" it's just a means to measure consumption. It's a pain in the ass but you'll get what you get. Even if you get a large meter, if the supply is low then it's low. You can request a large meter, but again that isn't a "power limit" it's just a means to measure consumption and they have different ones calibrated for different ranges. That's all.
We had this problem, it was real bad. We fought with the PEA for ages and filled out paper work with "head office" and finally after about 9 months they extended the 3 phase power all the way up the road which solved the power problem.
Was so bad I could only run 1 Aircon at a time + all other mandatory things like fridge & tv etc... I had 4 aircons installed.
I was on a 15/45 meter and it didn't matter. On bad days I would only get 185 volts to the house.
Anywho you might not have a problem, but it seems like an aggravating one I've encountered a lot due to me being spoiled and must have a climate controlled house & stuff.