Progress Update 01.07.23
It was a significant day today. With the final work to complete the waste water system, Ko-Kay Constructions finished the build contract. Work still outstanding by them, by way of a separate variation, is the construction of a wheel chair access ramp (we are planning ahead...).
I cannot speak highly enough of the company lead by Khun Pu. Apart from the render, which was less than satisfactory, the build quality as at today is highly satisfactory. The naysayers amongst readers of this thread will say, "Just wait 12 months." I'm sure there will be some problems, but how many buildings don't have problems 12 months on from completion? I'm confident our place will be fine (fingers crossed on the render).
Other work before we take occupancy:
- Installation of three A/C units, scheduled for 04.07.23
- Installation of Solar PV, confirmed for 03.07.23
- Kitchen installation, scheduled for mid August (see separate post below re Index Living Mall experience)
- Security screen and fly screen door installation, scheduled for early August.
Starting tomorrow I'll start carting up all our possessions from Australia that I can fit in the father in law's Hilux from the in-laws place to the house.
Following are photos from the last couple of days:
Local excavator operator back filling the waste water pipe trench
Waste water system pipe installation detail
Khun Pu and Change Nhy with a very happy owner at the completion of the build contract.