1 I assume you have checked ownership and boundaries?
yes all checked and have Chanote.
2 A brief local tour and enquiry will reveal need of 1-2 backfill
This is site specific ,dpend on slope,rainfall ,drainage
Working on that.
3 You need to let this settle,I left mine a year before foorings
I have been told one rainy season is enough by a few people that have already built in different place?
4 You are welcome to visit were about 2nrs N of Kwan Phayao
Thanks for that.
5 You say concrete, I built Superblock on an earhqauke,Phayp Pan area was near epicentre of severe recent quake
The quake didnt cause even a ripple where we are so all good there. No activity there for as far back as we can find.
6 Will you self plan ,off the shelf or bespoke architect ?
Undecided yet.
I think youve a year to source a small building team there are plenty of skilled workers, howvevr it depends on your priority time cash quality etc as many rural builders are also farmers
Also possibly plan for rainy season March-August best time to fill is now and build Sep 2106-Dec 2016 IMHO
The wifes dad is a farmer that does some building but always wood houses and the odd brick toilet extension. Neither of us think he would be up to a full brick build and any contacts he has are kinda the same
Its hard to know whether to trust the build to farmers/builders.