Progress Report.
Many will probably find this post as boring as batshit, but not for this little black duck. I'm wrapped to see the progress from Day 1 to today.
(for Day 1 image please see earlier posts)
The image below shows progress to date, from earlier this afternoon.
Day 16. Closing in on completing the columns. The crew down to eight today. Three of the team were away, making it a slow day by comparison. One column had to be redone after it failed QA - the Chang noticed me looking seriously at it after they removed the shuttering. A quick site meeting and it was kango hammered clean before the shutters were put back up. This crew continue to impress - eight travel each day from Roi Et with three staying on site (the three who were not at work today - maybe bad Som Tum?).
Hopefully the roofing and block work teams are as consistent and productive as this team.