5 Room Build Cost Breakdown |
|
|
|
|
|
Materials Breakdown |
|
|
|
|
|
THB |
|
Item |
6,000 |
|
Soil & digger – foundations |
5,400 |
|
Concrete for foundations – Readymix |
28,000 |
|
Steel rebar for ring beams & columns |
4,000 |
|
Plastic forms for ring beam and columns |
19,200 |
|
Concrete for Ring beam – Readymix |
9,000 |
|
Termite System installation & pipework |
5,300 |
|
Soak away concrete rings |
25,600 |
|
Concrete for internal floors – Readymix |
2,700 |
|
Soil/drainage Pipe |
5,200 |
|
Steel Mesh for car ports |
1,800 |
|
Stone |
1,800 |
|
Plastic sheeting for floor tanking |
114,000 |
|
Groundworks & Foundations |
|
|
|
18,500 |
|
Aerated blocks 500@ 18.5 |
880 |
|
Cement for aerated blocks |
7,000 |
|
Concrete block for Outside walls |
4,500 |
|
Cement for render |
3,600 |
|
Sand for render |
300 |
|
Fine bar for blockwork |
|
|
|
|
|
|
34,780 |
|
Walls (incomplete) |
|
|
|
|
|
|
44,700 |
|
Steel for Roof trusses |
550 |
|
Paint for Steel |
650 |
|
Welding rod |
5,550 |
|
Facia Cement board = conwood |
35,610 |
|
Roof sheeting and fixings |
|
|
|
87,060 |
|
Roofing (incomplete) |
|
|
|
|
|
|
8,900 |
|
Window inside = louvred aluminuim 5 * 1780 |
17,150 |
|
Window outside = UPVC 7 * 2450 |
14,560 |
|
Window grill = Stainless Steel 7 * 2080 |
4,950 |
|
Wood door surround = 990 *5 |
6,750 |
|
PVC door surrounds 1350* 5 |
4,100 |
|
Taps & Showers |
6,250 |
|
Toilets |
5,400 |
|
Sinks |
|
|
|
68,060 |
|
Furniture (incomplete) |
|
|
|
|
|
|
303,900 |
|
Material Total |
|
|
|
|
|
|
Contractor – stage payments |
|
|
|
|
|
THB |
|
Item |
68,000 |
|
1st payment for ground work, ring beam and uprights |
68,000 |
|
2nd payment for walls and roof |
68,000 |
|
Not yet paid |
68,000 |
|
Not yet paid |
58,000 |
|
Not yet paid |
330,000 |
|
Material Total |
|
|
|
|
|
|
633,900 |
|
Overall Total |
|
|
|