Replies should be interesting!
To Tony Hayward
We are looking forward to your testimony before the Subcommittee on Oversight and
Investigations on Thursday, June 17,2010, about the causes of the blowout ofthe Macondo well
and the ongoing oil spill disaster in the Gulf of Mexico. As you prepare for this testimony, we
want to share with you some of the results of the Committee's investigation and advise you of
issues you should be prepared to address.
The Committee's investigation is raising serious questions about the decisions made by
BP in the days and hours before the explosion on the Deepwater Horizon. On April 15, five days
before the explosion, BP's drilling engineer called Macondo a "nightmare well." In spite of the
well's difficulties, BP appears to have made multiple decisions for economic reasons that
increased the danger of a catastrophic well failure. In several instances, these decisions appear to
violate industry guidelines and were made despite warnings from BP's own personnel and its
contractors. In effect, it appears that BP repeatedly chose risky procedures in order to reduce
costs and save time and made minimal efforts to contain the added risk.
At the time of the blowout, the Macondo well was significantly behind schedule. This
appears to have created pressure to take shortcuts to speed finishing the well. In particular, the
Committee is focusing on five crucial decisions made by BP: (I) the decision to use a well
design with few barriers to gas flow; (2) the failure to use a sufficient number of "centralizers" to
prevent channeling during the cement process; (3) the failure to run a cement bond log to
evaluate the effectiveness of the cement job; (4) the failure to circulate potentially gas-bearing
Mr. Tony Hayward
June 14,20 10
Page 2
drilling muds out of the well; and (5) the failure to secure the wellhead with a lockdown sleeve
before allowing pressure on the seal from below. The common feature of these five decisions is
that they posed a trade-off between cost and well safety.
Well Design. On April 19, one day before the blowout, BP installed the final section of
steel tubing in the well. BP had a choice of two primary options: it could lower a fu ll string of
"casing" from the top of the wellhead to the bottom of the well, or it could hang a " liner" from
the lower end of the casing already in the well and install a "tieback" on top of the liner. The
liner-tieback option would have taken extra time and was more expensive, but it would have
been safer because it provided more barriers to the flow of gas up the annul ar space surrounding
these steel tubes. A BP plan review prepared in mid-April reconunended against the full string
of casing because it would create "an open annulus to the wellhead" and make the seal assembly
at the wellhead the "only barrier" to gas flow if the cement job failed. Despite thi s and other
warnings, BP chose the more risky casing option, apparently because the liner option would have
cost $7 to $10 million more and taken longer.
Centralizers. When the fina l string of casing was installed, one key chall enge was
making sure the casing ran down the center of the well bore. As the American Petroleum
Institute's recommended practices explain, if the casing is not centered, "it is difficu lt, ifnot
impossible, to displace mud effectively from the narrow side of the annulus," resulting in a faiku
cement job. Halliburton, the contractor hired by BP to cement the well, warned BP that the well
could have a "SEVERE gas flow problem" if BP lowered the final string of casing with onl y six
centrali zers instead of the 21 recommended by Halliburton. BP rejected Halliburton's advice to
use additional centralizers. In an e-mail on April 16, a BP official involved in the decision
explained: " it will take 10 hours to install them . .. . I do not like this." Later that day, another
official recognized the risks of proceeding with insuffi cient centralizers but commented: "who
cares, it's done, end of story, will probably be fi ne."
Cement Bond Log. BP's mid-April plan review predicted cement failure, stating
"Cement simulations indicate it is unlikely to be a successful cement job due to formation
breakdown." Despite this warning and Halliburton's prediction of severe gas flow problems, BP
did not run a 9- to 12-hour procedure called a cement bond log to assess the integrity of the
cement sea l. BP had a crew from Schlumberger on the rig on the morning of April 20 for the
purpose of rUlUling a cement bond log, but they departed after BP told them their services were
not needed. An independent expel1 consulted by the Committee called this decision "horrib ly
neg I i gent. "
Mud Circulation. In exploratory operations like the Macondo well, wells are generally
filled with weighted mud during the drilling process. The American Petroleum Insti tute (API)
recommends that oil companies full y circulate the drilling mud in the well from the bottom to the
top before commencing the cementing process. Circulating the mud in the Macondo well could
have taken as long as 12 hours, but it would have allowed workers on the rig to test the mud for
Mr. Tony Hayward
June 14, 2010
Page 3
gas influxes, to safely remove any pockets of gas, and to eliminate debris and condition the mud
so as to prevent contamination of the cement. BP decided to forego this safety step and conduct
only a partial circulation of the drilling mud befo re the cement job.
Lockdown Sleeve. Because BP elected to use just a single string of casing, the Macondo
well had just two barriers to gas flow up the annular space around the final string of casing: the
cement at the bottom of the well and the seal at the wellhead on the sea floor. The decision to
use insuffi cient centralizers created a significant ri sk that the cement job would channel and fail ,
while the deci sion not to run a cement bond log denied BP the opportunity to assess the status of
the cement job. These decisions would appear to make it crucial to ensure the integrity of the
seal assembly that was the remaining barrier against an influx of hydrocarbons. Yet, BP did not
deploy the casing hanger lockdown sleeve that would have prevented the seal from being blown
out from below.
These five questionable decisions by BP are described in more detail below. We ask that
you come prepared on Thursday to address the concerns that these decisions raise about BP's
actions.
Background
BP stmt ed drilling the Macondo well on October 7, 2009, using the Marianas ri g. This
rig was damaged in Hurricane Ida on November 9, 2009. As a result, BP and the rig operator,
Transocean, replaced the Marianas ri g with the Deepwater Horizon. Drilling with the Deepwater
Hori zon started on February 6, 20 I O.
The Deepwater Hori zon rig was expensive. Transocean charged BP approximately
$500,000 per day to lease the ri g, plus contractors' fees.] BP targeted drilling the well to take 51
days and cost approximately $96 million?
The Deepwater Horizon was supposed to be drilling at a new location as early as March
8,20 103 In fact, the Macondo well took considerably longer than plarmed to complete. By
April 20, 20 10, the day of the blowout, the rig was 43 days late for its next drilling location,
which may have cost BP as much as $21 million in leasing fees alone. It also may have set the
context for the series of deci sions that BP made in the days and hours before the blowout.
] According to the terms of the contract, the daily rate would range from $458,000 in
March 2008 to $5 17,000 in September 20 I O. See Transocean, Transocean Fleet Update, fn. II
(Apr. 13, 20 I 0) (online at http ://www.deepwater.com/fw/mainiFleet-Update-Report-58.html).
2 BP, GOM Exploration Wells Me 252 #i - Macondo Prospect Well in/ormation (Sept.
2009) (BP-HZN-CEC0087 14).
J Testimony of Steve Tink, BP, Health, Safety and Environmental Manager, before the
U.S. Coast Guard/MMS Marine Board of Investigation (May 26, 20 10).
Mr. Tony Hayward
June 14, 2010
Page 4
Well Design
Deepwater well s are drilled in sections. The bas ic process involves drilling through rock,
installing and cementing casing to secure the well bore, and then drilling deeper and repeating the
process. On April 9, 2010, BP fini shed drilling the last section of the well. The final section of
the well bore extended to a depth of 18,360 feet below sea level, which was 1,192 feet below the
casing that had previously been inserted into the we1l 4
At this point, BP had to make an important well design deci sion: how to secure the final
1,192 feet of the well. On June 3, Halliburton's Vice President of Cementing, Tommy Roth,
briefed Committee staff about the two primary options available to BP. One option involved
hanging a steel tube called a " liner" from a liner hanger on the bottom of the casing already in
the well and then inserting another steel liner tube called a "tieback" on top of the liner hanger.
The other option involved rurming a single string of steel casing from the seafloor all the way to
the bottom of the well. Mr. Roth informed the Committee that "Liner/Tieback Casing provides
advantage over full string casing with redundant barriers to annul ar flow."s In the case of a
single string of casing, there are just two barriers to the flo w of gas up the arullliar space that
surrounds the casing: the cement at the bottom of the well and the seal at the wellhead. Mr.
Roth told the Committee that in contrast, "Liner/Tieback provides four barri ers to annular
flow.,,6 They are (I ) the cement at the bottom of the well, (2) the hanger seal that attaches the
liner to the ex isting casing in the well , (3) the cement that secures the tieback on top of the liner,
and (4) the seal at the wellhead. The liner-tieback option also takes more time to install,
requiring several addit ional days to complete.
Internal BP documents indicate that BP was aware of the ri sks of the single casing
approach. An undated "Forward Plan Review" that appears to be from mid-April recommended
against the single string of casing because of the ri sks. According to this document, "Long string
of casing . .. was the primary option" but a "Liner ... is now the recommended option.")
4 BP, PowerPoint Presentation, Washington Briefing, Deepwater Horizon Interim
Incident In vestigation at 4 (May 24, 20 I 0).
S Briefing by Tonuny Roth, Vice President of Cementing, Halliburton, to House
Committee on Energy and Commerce Staff (June 3, 2010); Halliburton, PowerPoi nt
Presentation, Energy and Commerce Commillee Staff Briefing at 12 (J une 3, 20 10).
6 Id. at 6.
) BP, MC 252#1 Macondo, TD Forward Plan Review - Production Casing & TA
Options, at 9. (Apr. 20 I 0) (BP-HZN-CEC-221 09). The documents provided to the Committee
from BP contain three versions of this document. This one and a second nearly identical version
(BP, MC 252#1 Macondo, TD Forward Plan Review - Production Casing & TA Options (Apr.
2010)) (BP-HZN-CEC-22025) recommend against a single string casing and in favor ofa liner
Mr, Tony Hayward
June 14,2010
Page 5
The document gave four reasons against using a single string of casing, They were:
• "Cement simulations indicate it is unlikely to be a successful cement job due to formation
breakdown, "
• "Unable to fulfill MMS regulations of 500' of cement above top HC zone,"
• "Open annulus to the wellhead, with " , seal assembly as only barrier."
• "Potential need to verify with bond log, and perform remedial cementjob(s),,,g
In contrast, according to the document, there were four advantages to the liner option:
• "Less issue with landing it shallow (we can also ream it down),"
• "Liner hanger acts as second barrier for HC in arlllulus,"
• "Primary cement job has slightly higher chance for successfiil cement lift,"
• "Remedial cement job, if required, easier to justify to be left for later." 9
Communications between employees ofBP confirm they were evaluating these
approaches, On April 14, Brian Morel, a BP Drilling Engineer, e-mailed a colleague, Richard
Miller, about the options, His e-mail notes: "this has been [aJ nightmare well which has
everyone all over the place, ,, lo
Despite the risks, BP chose to install the singl e string of casing instead of a liner and
tieback, applying for an amended permit on April 15,11 The company's application stated that
the full casing string would start at 9 7/8 inches diameter at the top of the well and narrow to 7
inches diameter at the bottom, 12 This application was approved on the same day,13
approach, The third version recommends in favor of the single string of casing and is di scussed
below,
g ]d, "HC" stands for hyd rocarbon,
9 Id, at 10,
10 E-mail from Brian Morel, Drilling Engineer, BP, to Ri chard Miller, BP (Apr. 15, 20 I 0)
(BP-HZN-CEC-2 1857),
II BP, Form MMS 123A1123S - Electronic Vers ion, Applicationfor Revised Bypass (Apr.
15,20 I 0) (BP-HZN-CECO I8357),
12 Id,
IJ E-mail from Frank Patton, MMS, to Heather Powell, JC Connor Consulting
("Modifi cation of Permit to Bypass as Location Surface Lease: 032306 Surface ATea: MC
Surface Block: 252 Bottom Lease: 032306 Bottom ATea: MC Bottom Block: 252 Well Name:
001 Assigned API Number: 608174116901 has been approved, as of2010-04-15 14:39:39,0")
(Apr. 14,20 10), Ms, Powell then forwarded the approval to BP, E-mail from Heather Powell,
Mr. Tony Hayward
June 14, 2010
Page 6
The decision to run a single string of casing appears to have been made to save time and
reduce costs. On March 25 , Mr. Morel e-mailed Alli son Crane, the Materials Management
Coordinator for BP's Gulf of Mexico Deepwater Exploration Unit, that the long casing string
" saves a lot of time ... at least 3 days. ,,14 On March 30, he e-mailed Sarah Dobbs, the BP
Completions Engineer, and Mark Hafl e, another BP Drilling Engineer, that "[ n Jot running the
tieback ... saves a good deal of time/money.,,15 On April IS, BP estimated that using a liner
instead of the single string of casing "will add an additional $7 - $10 MM to the completion
cost.,,16 The same document calls the single string of casing the "[b Jest economic case and well
integrity case for future completion operations.,,17
Around this time, BP prepared another undated version of its "Forward Plan Review."
Notably, this version of the document reaches a di ffe rent conclusion than the other version,
calling the long string of casing "the primary option" and the liner "the contingency option. ,,18
Like the other version of the plan review, this version acknowledges the risks of a single string of
casing, but it now descri bes the option as the "Best economic case and well integrity case for
future completion operations. ,,19
Centralizers
Centralizers are attaclm1ents that go around the casing as it being lowered into the well to
keep the casing in the center of the borehol e. If the well is not properly centered prior to the
cementing process, there is increased ri sk that channels will form in the cement that allow gas to
flow up the annular space around the casing. API Recommended Practice 65 explains: "If
casing is not centrali zed, it may lay near or against the borehole wall. ... It is difficult, if not
JC COImor Consulting, to Mark Hafle, Senior Drilling Engineer, BP (Apr. 15,201 0) (BP-HZNCEC021033).
14 E-mail from Brian Morel, Drilling Engineer, BP, to Alli son Crane, Materi als
Management Coordinato r, BP Gulf of Mexico Deepwater Exploration (Mar. 25, 2010). (BPHZN-
CEC02 1880).
15 E-mail from Brian Morel, Drilling Engineer, BP, to Sarah Dobbs, Completions
Engineer, BP, and Mark Hafl e, Senior Drilling Engineer, BP (Mar. 30,20 I 0) (BP-HPCEC02
1948).
16 BP, Drilling & Compielions MOC In iliale (Apr. 15,20 I 0) (BP-HZN-CEC02 1656).
17 / d.
18 BP, TD Forward Plan Review, Produclion Casing & TA Oplions at 6-7 (undated) (BPHZN-
CEC-022 145).
19 1d.
Mr. Tony Hayward
June 14, 20 10
Page 7
imposs ible, to displace mud effectively from the nan-ow side of the annulus if casing is poorly
centralized. This results in bypassed mud charll1els and inability to achieve zonal isolation.,,20
On April 15, BP informed HallibUlton's Account Representative, Jesse Gagliano, that BP
was planning to use six centralizers on the final casing string at the Macondo well. Mr. Gagliano
spent that day nUU1ing a computer analysis of a number of cement design scenarios to determine
how many centralizers would be necessary to prevent channeling21 With ten centralizers, the
modeling resulted in a "MODERATE" gas flow problem22 Mr. Gagliano's modeling showed
that it would require 21 centralizers to achieve only a "MINOR" gas flow problem23
Mr. Gagliano informed BP of these results and recommended the use of 21 centralizers24
After running a model with ten centralizers, Mr. Gagliano e-mailed Brian Morel, BP's drilling
engineer, and other BP officials, stating that the model "now shows the cement charll1eling" and
that ''I'm going to run a few scenarios to see if adding more centralizers will help us or not.,,25
Twenty-five minutes later, Mr. Morel e-mailed back:
We have 6 centrali zers, we can run them in a row, spread out, or any combination of the
1\\10. It ' s a vertical hole, so hopefully the pipe stays centralized due to gravity. As far as
changes, it's too late to get any more product on the rig, our only option[] is to rearrange
placement of these centralizers26
20 API, Recommended Practice 65-Part 2, Isolating Potential Flow Zones During Well
Construction, 4.6.5.8. , at 28.
21 House Committee on Energy and Commerce, Transcribed Interview of Jesse Marc
Gagliano, at 26 (June 11 , 20 10).
22 Halliburton, 9 7/8 " X 7" Production Casing Design Report (Apr. 15,2010)
(HAL_DO 1 0592).
23 HallibUlton, 9 7/8 " X 7" Production Casing Design Report (Apr. 15,20 10)
(HAL_DO 1 0699).
24 House Committee on Energy and Commerce, Transcribed Interview of Jesse Marc
Gagliano, at 8 (June 11 , 20 10).
25 E-mail from Jesse Gagliano, Account Representative, Halliburton, to Mark Hafle,
Senior Drilling Engineer, BP, Brian Morel, Drilling Engineer, BP, Brett Cocales, Operations
Drilling Engineer, BP, and Gregory Walz, Drilling Team Leader, BP (Apr. 15,20 10)
(HAL_DO 1 0650).
26 E-mail from Brian Morel, Drilling Engineer, BP, to Jesse Gagliano, Account
Representative, Hallib1ll10n, Mark Hafle, Senior Drilling Engineer, BP, Brett Cocales,
Operations Drilling Engineer, BP, and Gregory Walz, Drilling Team Leader, BP (Apr. 15, 20 10)
(HAL_DO 1 0648).
Mr. Tony Hayward
June 14,2010
Page 8
The following day, April 16, the issue was elevated to John Guide, BP's Well Team
Leader, by Gregory Walz, BP's Drilling Engineering Team Leader. Mr. Walz informed Mr.
Guide: "We have located 15 Weatherford centrali zers with stop collars ... in Houston and
worked things out with the rig to be able to fly them out in the morning." The decision was
made because "we need to honor the modeling to be consistent with our previous decisions to go
with the long string.,,27 Mr. Walz explained: "I wanted to make sure that we did not have a
repeat of the last Atlantis job with questionable centralizers going into the hole. ,,28 Mr. Walz
added: "I do not like or want to di srupt your operations . . .. I know the planning has been
lagging behind the operations and I have to turn that around. ,,29
In his response, Mr. Guide raised objections to the use of the additional centrali zers,
writing: " it will take 10 hrs to install them . .. . I do not like thi s and ... I [am] very concerned
about using them. ,,30
An e-mail from Brett Cocales, BP's Operations Drilling Engineer, indicates that Mr.
Guide's perspective prevailed. On April 16, he e-mailed Mr. Morel:
Even if the hole is perfectl y straight, a straight piece of pipe even in tension will not seek
the perfect center of the hole unless it has something to centralize it.
But, who cares, it's done, end of story, will probably be fine and we' ll get a good cement
job. I would rather have to squeeze than get stuck .... So Guide is right on the
rI.S kJ rewar d equatI.o n. 31
On April 17, Mr. Gagliano, the Halliblllton account representative, was informed that BP
had decided to use only six centrali zers32 He then ran a model using seven centralizers and
27 E-mail from Gregory Walz, Drilling Team Leader, BP, to Jolm Guide, Well Team
Leader, BP (Apr. 16,201 0) (BP-HZN-CEC0022433).
28 Id.
29 Id.
30 Id.
31 E-mail from Brett Cocales, Operat ions Drilling Engineer, BP, to Brian Morel, Drilling
Engineer, BP (Apr. 16, 20 10) (BP-HZN-CEC022670).
32 House Committee on Energy and Commerce, Transcri bed Interview of Jesse Marc
Gagliano, at 40-41 (J une 11 ,201 0).
Mr. Tony Hayward
June 14,20 10
Page 9
found this would likely produce channeling and a failure of the cement job33 His April 18
cementing design report states: "well is considered to have a SEVERE gas flow problem.,,34
Mr. Gagliano said that BP was aware of the risks and proceeded with knowledge that his report
indicated the well would have a severe gas flow problem35
Mr. Gagliano's findings should not have been a surprise to BP. As noted above, BP's
mid-April plan review found that if BP used a single string of casing, as BP had decided to do,
"Cement simulations indicate it is unlikely to be a successful cementjob.,,36 Nonetheless, BP
ran the last casing with only six centralizers37
Cement Bond Log
A cement bond log is an acoustic test that is conducted by rurming a tool inside the casing
after the cementing is completed. The cement bond log determines whether the cement has
bonded to the casing and surrounding formations. If a channel that would allow gas flow is
found , the casing can be perforated and additional cement injected into the armular space to
repair the cement job.
Mr. Roth, the Halliburton Vice President of Cementing, informed the Committee staff
that BP should have conducted a cement bond log. According to Mr. Roth, "If the cement is to
be relied upon as an effective barrier, the well owner must perform a cement evaluation as part of
I · .. ,,38 a compre lenSlve systems II1tegnty test.
J3 Id. at 8. Mr. Gagliano told the Conullittee that at the time he ran a model with seven
centralizers, he knew of BP's decision to use only six. He told the Conunittee that running a
model with seven centralizers demonstrated that the difference between six and seven
centralizers would be unlikely to affect the outcome of the modeling.
34 HallibUl10n, 9 7/8" X 7" Production Casing Design Report (Apr. 18,20 10)
(HAL_00I0955).
35 House Committee on Energy and Commerce, Transcribed Interview of Jesse Marc
Gagliano, at 43-45 (June 11 ,20 I 0).
36 BP, MC 252#1 Macondo, TD Forward Plan Review - Production Casing & TA
Options, at 9. (Apr. 20 I 0) (BP-HZN-CEC-22I 09).
37 BP, Daily Operations Report - Partners (Completion) (Apr. 18 , 2010)
(HAL_00282 10).
38 Briefing by Tommy Roth, Vice President of Cementing, Halliburton, to House
Committee on Energy and Commerce Staff (June 3, 2010); Halliburton, PowerPoint
Presentation, Energy and Commerce Commillee Staff Briefing at 12 (June 3, 20 10).
Mr. Tony Hayward
June 14,2010
Page 10
Minerals Management Service (MMS) regulations also appear to direct a cement bond
log or equivalent test at the Macondo well. According to the regulations, if there is an indication
of an inadequate cement job, the oil company must "(1) Pressure test the casing shoe; (2) Run a
temperature survey; (3) Run a cement bond log; or (4) Use a combination of these techniques."J9
In the case of the Macondo well, the HallibUlton and internal BP warnings should have served as
an indication of a potentially inadequate cement job.
On April 18, BP flew a crew from Schlumberger to the rig. As described in a
Schlumberger timeline, "BP contracted with Schlumberger to be available to perform a cement
bond log ... should BP request those services.,,40 But at about 7:00 a.m. on the morning of April
20, BP told the Schlumberger crew that their services would not be required for a cement bond
log test41 As a result, the Schlumberger crew departed the Deepwater Horizon at approximately
II: 15 a.m. on a regularly scheduled BP helicopter flight 42 The Schlumberger crew was
scheduled for departure before pressure testing of the well had been completed, indicating that
the results of those tests were not a factor in BP's decision to send the crew away without
4' conducting a cement bond log. >
BP's decision not to conduct the cement bond log test may have been driven by concerns
about expense and time. The cement bond log would have cost the company over $ 128,000 to
complete44 [n comparison, the cost of canceling the service was just $10,000.45 Moreover, Mr.
Roth of Halliburton estimated that conducting the test would have taken an additional 9 to 12
hours46 Remediating any problems found with the cementing job would have taken still more
. 47 lime.
39 30 CFR § 250.428.
40 Schlumberger, Mississippi Canyon Block 252 Timeline (undated) (SLB-EC-000002).
41 ld.
42 ld
43 Briefing by Mark Bly, Group Vice President for Safety & Operations, BP, to House
Committee on Energy and Commerce Staff (May 25, 20 10).
44 Schlumberger, Estimated Costs of Equipment/Labor to Pelform the Contingent
Services Identified by BP and the AClual COS/S Upon Cancellalion (SLB-EC-000909).
45 ld.
46 Briefing by Tommy Roth, Vice President of Cementing, Halliblllton, to House
Committee on Energy and Commerce Staff (June 3, 2010).
47 A BP document indicates that the company would rely on lost mud "returns" during
the cementing process as a trigger for conducting a cement bond log. BP, GOM Exploralion
Wells MC 252 #lSTOOBPOl- Macondo Prospecl 7" x 9- 7/S" lnlerval at 3 (Apr. 15,2010) (BPMr.
Tony Hayward
June 14,2010
Page II
The Committee staff asked an independent engineer with expel1ise in the analysis of well
fai lure about BP's decision not to conduct a cement bond log. The engineer, Gordon Aaker, Jr.,
P.E. , a Failure Anal ysis Consultant with the firm Engineering Services, LLP, said that it was
"unheard of" not to perform a cement bond log on a well using a single casing approach, and he
described BP's decision not to conduct a cement bond log as "horribly negligent. ,,48 Another
independent expert consulted by the Committee, Jolm Martinez, P.E., told the committee that
"cement bond or cement evaluation logs should always be used on the production string.,,49
Mud Circulation
Another questionable decision by BP appears to have been the failure to circulate fu lly
the drilling mud in the well before cementing. This procedure, known as "bottoms up," involves
circulating dri lling mud from the bottom of the well all the way to the sur face. Bottoms up has
several purposes: it allows workers on the rig to test the mud for influxes of gas; it permits a
controlled release of gas pockets that may have entered the mud; and it ensures the removal of
well cuttings and other debris from the bottom of the well, preventing contamination of the
cement.
API 's guidelines recommend a full bottoms up circulation between rUlming the casing
and beginning a cementing job. The reconmlended practice states that "when the casing is on
bottom and before cementing, circulating the drilling fluid will break its gel strength, decrease its
viscosi ty and increase its mobility. The dri lling fluid should be conditioned until equilibrium is
achieved .... At a minimum, the hole should be conditioned for cementing by circulating 1.5
annular volumes or one casing volume, whichever is greater. ,,50
HZN-CECO I7621). Mr. Gagliano of Halliburton told the Committee that lost returns are not a
reliab le indicator of channeling: "the amount of returns would not tell you if there's charll1eling
or not. Full returns just indicates the amount of fluid you' re pumping into the well bore, you' re
getting the equal or very close to equal volume back at surface, which is telling you that you' re
not fracturing any fluids into the format ion or losing any fluid s. It 's not really an indication of
channeling." House Committee on Energy and Conunerce, Transcribed Interview of Jesse Marc
Gagliano, at 86 (June 11 , 20 10).
48 Briefing by Gordon Aaker, Jr., P.E., Failure Anal ys is Consultant with Engineering
Services, L.P. (Houston), to House Committee on Energy and Conullerce Staff (June 10, 20 10).
49 E-mail from John Martinez, P.E.,an independent production specialist on well bore
construction, to House Committee on Energy and Commerce Staff (June 10,2010).
50 API, Recommended Practice 65-Part 2, Isola/ing Po/en/ial Flow Zones During Well
Cons/rile/ion, 4.8.4., at 36-37.
Mr, Tony Hayward
June 14, 20 10
Page 12
BP's April 15 operations plan called for a full bottoms up procedure to "circulate at least
one ( I) casing and drill pipe capacity, if hole conditions allow. ,,'1 Halliburton Account
Representative Jesse Gagliano said it was also "Halliburton's recommendation and best practice
to at least circulate one bottoms up on the well before doing a cement job,,,52 According to Mr.
Gagliano, a Halliburton engineer on the rig raised the bottoms up issue with BPS}
Despite the BP operations plan and the Hallib1ll10n recommendation, BP did not fully
circulate the mud, Instead, it chose a procedure "written on the rig" which Mr. Gagliano "did not
get input in, ,,54 BP's final procedure called for circulating just 26 1 barrels of mud, just a small
fraction of the mud in the Macondo well. 55 Mr. Roth of Hallibul10n told the Committee that one
reason for the decision not to circulate the mud could have been a desire for speed, as fully
circulating the mud could have added as much as 12 hours to the operation56 Mr, Gagliano
expressed a similar view, saying, "the well probably would not have handled too high of a rate,
So it would take a little bit", longer than usual to circulate bottoms up in this case, ,,57
Lockdown Sleeve
A final question relates to BP's deci sion not to install a critical apparatus to lock the
wellhead and the casing in the seal assembly at the seafloor. When the casing is placed in the
wellhead and cemented in place, it is held in place by gravity, Under certain pressure conditions,
however, the casing can become buoyant, rising up in the wellhead and potentially creating an
opportunity for hydrocarbons to break through the wellhead seal and enter the riser to the
surface, To prevent this, a casing hanger lockdown sleeve is installed,
On June 8, 20 I 0, Transocean briefed Committee staff on its investigation into the
potential causes of the explosion on board the Deepwater Horizon, In the presentation,
Transocean li sted the lack of a lockdown sleeve as one of its "areas of investigation," Slide
51 BP, GOM Exploration Wells, Me252 #ISTOOPBPOI - Macondo Prospect 7" X 9 7/8 "
Interval, Rev, H.2 at 6 (Apr. 15, 20 10) (BP-HZN-CEC-O 1762 1),
52 House Committee on Energy and Commerce, Transcribed Interview of Jesse Marc
Gagliano, at 57 (June 11 , 20 10),
D ld,at 6 1.
54 Id, at 57,
55 Id, at 60,
56 Briefing by Tommy Roth, Vice President of Cementing, Hallib1ll10n, to House
Committee on Energy and Commerce Staff (June 3, 20 I 0),
57 House Committee on Energy and Commerce, Transcribed Interview of Jesse Marc
Gagliano, at 65-66 (June 11 , 20 10),
Mr. Tony Ha)'\vard
June 14, 2010
Page 13
seven of Transocean's presentation asks: "Were Operator procedures appropriate?" A subpoint
details: "Operator did not run lock down sleeve prior to negative test or displacement.,,58 Mr.
Roth of Halliburton raised a similar concern in his June 3 briefing for Committee staff59
In BP's planned procedure for the well, BP describes two options involving the lockdown
sleeve. BP was seeking permission from MMS to install the final cement plug on the well at a
lower depth than previously approved. If permission was granted, BP's plan was to displace the
drilling mud in the riser with seawater and install the cement plug prior to installation of the
casing hanger lockdown sleeve. BP's alternative plan, if MMS did not approve the proposed
depth of the final cement plug, was to run the lockdown sleeve first, before installing the cement
plug at a shallower depth 6 0 On April 16, Brian Morel, BP's drilling engineer, e-mailed BP staff
that: "We are still waiting for approval of the depatture to set our surface plug . ... Ifwe do not
get this approved, the displacemenUplug will be completed shallower after running the LDS.,,61
The LDS stands for the lockdown sleeve.
Conclusion
The Conm1ittee's investigation into the causes of the blowout and explosion on the
Deepwater Horizon rig is continuing. As our investigation proceeds, our understanding of what
happened and the mistakes that were made will undoubtedly evolve and change. At this point in
the investigation, however, the evidence before the Committee calls into question multiple
decisions made by BP. Time after time, it appears that BP made decisions that increased the risk
of a blowout to save the company time or expense. If this is what happened, BP's carelessness
and complacency have inflicted a heavy toll on the Gulf, its inhabitants, and the workers on the
n g.
58 Transocean, PowerPoint Presentation, Deepwater Horizon Incident - Internal
Investigation: Investigation Update - Interim Report at 7 (June 8, 2010).
59 Briefing by Tommy Roth, Vice President of Cementing, Hallibutton, to House
Committee on Energy and Commerce Staff (June 3, 2010).
60 BP, GOM Exploration Wells Me 252 #lSTOOBP01- Macondo Prospect 7" x 9- 7/8"
Interval at 8 (Apr. 15, 2010) (BP-HZN-CECOI7621).
61 E-mail from Brian Morel, Drilling Engineer, BP, to Ronald Sepulvado et al. (Apr. 16,
20 10) (BP-HZN-CEC02282 I).
Mr. Tony Hayward
June 14, 2010
Page 14
During your testimony before the Committee, you will be asked about the issues raised in
this letter. This will provide you an opportunity to respond to these concerns and clarify the
record. We appreciate your willingness to appear and your cooperation in the Committee's
investigation.
Henry A. Waxman
Chairman
Enclosure
cc: The Honorable Joe Barton
Ranking Member
The Honorable Michael C. Burgess
Ranking Member
Sincerely,
~~
Bart Stupak
Chairman
Subcommittee on Oversight and Investigations
Subcommittee on Oversight and Investigations