    The shed in my head turned out a bit different in reality!

    As we are moving up country in 25 days we needed somewhere to house my extra things that won't be going in the house...plus bags of fertiliser and other farm stuff.

    The scary thing is how cost quickly escalated. I took up 150k baht but had to draw out another 50k baht from ATM, borrow 45k baht from MIL and we still aren't finished!

    I'll put up some pix's if I can.

    https://www.dropbox.com/sc/jakf90ki2...ZhIVvycx6Q93Va
    Last edited by Hoops; 28-11-2014 at 10:10 PM.

  2. #2
    Thailand Expat
    Join Date
    Jun 2014
    Last Online
    @
    Posts
    18,022
    Must be one hell of a shed for B250,000...
    Could build a reasonable bungalow for that.

    I trust the extra things you're looking to store are easily conducive to local climes.

  3. #3
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Well dropbox works through a link!

    Here's a bit more.

    https://www.dropbox.com/sc/93gejzfml...nWEvdg-xCJREYa

  4. #4
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Quote Originally Posted by thaimeme View Post
    Must be one hell of a shed for B250,000...
    Could build a reasonable bungalow for that.

    I trust the extra things you're looking to store are easily conducive to local climes.
    I think it's going to cost 350k baht.

    It's 6.5M wide x 12M long with 4M high door openings.

    "I trust the extra things you're looking to store are easily conducive to local climes " Hard to say. The climate is not too tropical.

  5. #5
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    A few more pix's of the "MEGA PROJECT" as we call it!

    https://www.dropbox.com/sc/kh684e00g...On-PLND03YbxQa

  6. #6
    Member
    Join Date
    Jan 2014
    Last Online
    03-04-2015 @ 09:06 PM
    Posts
    633
    Quote Originally Posted by Hoops
    I think it's going to cost 350k baht.
    That's crazy.

  7. #7
    Member
    Nathan Napalm's Avatar
    Join Date
    Nov 2014
    Last Online
    @
    Location
    9/11 was an inside job
    Posts
    254
    Quote Originally Posted by Hoops
    I think it's going to cost 350k baht. It's 6.5M wide x 12M long with 4M high door openings.

  8. #8
    RIP pseudolus's Avatar
    Join Date
    Jan 2012
    Last Online
    @
    Posts
    18,083
    Is it made of gold?

  9. #9
    Thailand Expat
    palexxxx's Avatar
    Join Date
    Jun 2011
    Last Online
    @
    Location
    Chiang Mai
    Posts
    4,141
    Where are you getting these prices from? Are your in-laws 'helping' you with your build?

  10. #10
    5 4 Knoll
    david44's Avatar
    Join Date
    Aug 2011
    Last Online
    @
    Location
    At Large
    Posts
    21,088
    Does the 350k include buying the land ,otherwise its way over the top even for Hebel tile finish,for block and concrete 100k tops

  11. #11
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Hi folks, it's only my shed for now, later it maybe a processing plant for something we are planning. The builder charged me 48k baht. The rest of the cost is material. CPAC charged me 1700 baht a cubic but I think the bastard driver dropped of one cubic (or more) for a mate cos the first truck load was short, the missus got on the phone to CPAC but nothing was done. The next day we got a independent operator with a small truck that gave use the 3 metres we ordered and charged less per cubic.

    Anyway more pix's.
    https://www.dropbox.com/sh/fhjy9iwco...Hutqw6cZa?dl=0

  12. #12
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    I was surprised at the cost of everything. After getting a quote from TOA in Sak Lek we went up to Phitanulok and got prices at Thai Watsadu and Global House and both were dearer plus Thai Watsadu wanted 1900 baht extra for a big truck to deliver and Global house wanted 3400 baht for 2 smaller trucks. So TOA in Sak Lek got the order.

    https://www.dropbox.com/sh/2w6gy29nf...-E7pZOMNa?dl=0

  13. #13
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Some more pix's. They do thing's ass about here but in the end it works!

    https://www.dropbox.com/sh/sowr0641v...XWS3ZAFxa?dl=0

  14. #14
    Member
    Nathan Napalm's Avatar
    Join Date
    Nov 2014
    Last Online
    @
    Location
    9/11 was an inside job
    Posts
    254
    Quote Originally Posted by Hoops
    I was surprised at the cost of everything
    Bet you were mate

  15. #15
    5 4 Knoll
    david44's Avatar
    Join Date
    Aug 2011
    Last Online
    @
    Location
    At Large
    Posts
    21,088
    For what its worth remaininvisible when negotiating there is dual pricing eberywhere and a wealthy farlang is easy pickings.
    Also during my build when we employed no family as its so embarrassing to sack them
    We did sack only one pf probably 5o labourers and ttradesmen over 5 months,he was punctual friendly but a bricklayer in name only.

    Despite a unique design in Hebel of 3 houses Ive designed and been onvolved hands on in construction the speed and quality was best and done on budget.

    If you are not compteet to oversee the quality employ some on who is is my opinio for waht its worth.

    Good luck,as for deliveries need a checklist and checker just sendthem back unpaid if wrong
    Quote Originally Posted by Latindancer View Post
    I just want the chance to use a bigger porridge bowl.

  16. #16
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Quote Originally Posted by david44 View Post
    For what its worth remaininvisible when negotiating there is dual pricing eberywhere and a wealthy farlang is easy pickings.
    Also during my build when we employed no family as its so embarrassing to sack them
    We did sack only one pf probably 5o labourers and ttradesmen over 5 months,he was punctual friendly but a bricklayer in name only.

    Despite a unique design in Hebel of 3 houses Ive designed and been onvolved hands on in construction the speed and quality was best and done on budget.

    If you are not compteet to oversee the quality employ some on who is is my opinio for waht its worth.

    Good luck,as for deliveries need a checklist and checker just sendthem back unpaid if wrong
    Thanks for the advice David. The only family involved was the BIL who used his tractor to spread the crushed rock for the base in the shed. The across the soi neighbours son bought the 4 loads of crushed rock from the quarry which is only 45km away (90km round trip) and charged me 1000 a load for the truck...and the next day got a load of chook poo for the BIL who paid 1800 for a 160km round trip and 2 hours loading time. I reckon he ripped Anun and me off!

    More pix's:https://www.dropbox.com/sh/523e6oaqt...vk96Axpna?dl=0

  17. #17
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Quote Originally Posted by david44 View Post
    For what its worth remaininvisible when negotiating there is dual pricing eberywhere and a wealthy farlang is easy pickings.
    Also during my build when we employed no family as its so embarrassing to sack them
    We did sack only one pf probably 5o labourers and ttradesmen over 5 months,he was punctual friendly but a bricklayer in name only.

    Despite a unique design in Hebel of 3 houses Ive designed and been onvolved hands on in construction the speed and quality was best and done on budget.

    If you are not compteet to oversee the quality employ some on who is is my opinio for waht its worth.

    Good luck,as for deliveries need a checklist and checker just sendthem back unpaid if wrong
    Thanks for the advice David. The only family involved was the BIL who used his tractor to spread the crushed rock for the fill in the shed. The across the soi neighbours son bought the 4 loads of crushed rock from the quarry which is only 45km away (90km round trip) and charged me 1000 a load for the truck...and the next day got a load of chook poo for the BIL who paid 1800 for a 160km round trip and 2 hours loading time. I reckon he ripped Anun and me off!

    I live and learn!

    More pix's:https://www.dropbox.com/sh/523e6oaqt...vk96Axpna?dl=0

  18. #18
    Banned

    Join Date
    Jun 2011
    Last Online
    14-08-2015 @ 05:39 PM
    Location
    Ex-Pat Refugee in Thailand
    Posts
    9,579
    Hoops, FWIW, I paid 1900/cu.meter in the far north/ I should say my GC did. He was on lump sum, progress payments so in spite of what others here post even Thais pay the going rate.

    Nice shed, thin floor concrete as well shallow footings. Hope they serve you well.

  19. #19
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Quote Originally Posted by ltnt View Post
    Hoops, FWIW, I paid 1900/cu.meter in the far north/ I should say my GC did. He was on lump sum, progress payments so in spite of what others here post even Thais pay the going rate.

    Nice shed, thin floor concrete as well shallow footings. Hope they serve you well.
    It's 4" thick concrete...which will be fine for normal shed use. If we task it as a processing shed I'll have the local builder cut out 4 sections and have high strength concrete down as far as needed to keep the machine stable.

    A few more pix's:
    https://www.dropbox.com/sh/bx3ijcguq...AJp5uOAka?dl=0

  20. #20
    Member
    Join Date
    Jan 2014
    Last Online
    03-04-2015 @ 09:06 PM
    Posts
    633
    Quote Originally Posted by david44
    Despite a unique design in Hebel of 3 houses Ive designed and been onvolved hands on in construction the speed and quality was best and done on budget.
    Really?

  21. #21
    Banned

    Join Date
    Jun 2011
    Last Online
    14-08-2015 @ 05:39 PM
    Location
    Ex-Pat Refugee in Thailand
    Posts
    9,579
    Quote Originally Posted by Hoops
    It's 4" thick concrete
    That should do it. Did you put down a vapor barrier first? What about the shallow column piers?

  22. #22
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Quote Originally Posted by thaimeme View Post
    Quote Originally Posted by Fondles View Post
    Whats with the fuckin dropbox links ya fucken poof.

    Put the pics in the thread for fuck sake.
    Don't be so intolerant, Fiddles...

    Obvious Hoops is a newbie and perhaps doesn't know how to post images straight up yet - at least one can view the photos of reference.

    If he wishes to figure the system out later, he probably will.

    Relax, FFS.
    Wish I knew the secret way of doing that! Insert link is the only thing that shows up on the message command line.

  23. #23
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    The first stage is finished, so the next stage will continue when I return. Needs paint, gutters and roller doors and electrics to finish off.

    More pix's later!

  24. #24
    Thailand Expat
    toddaniels's Avatar
    Join Date
    Apr 2012
    Last Online
    06-09-2020 @ 10:42 AM
    Location
    Bangkok
    Posts
    1,904
    All I can say is that is one fucking expensive shed!!! Especially for one which appears to be between Nakhon Nowhere and "where-the-fuck-are-we" Thailand!

    There isn't a thai in this country who'd fork out that kinda dosh for what the pix show..

    Then again, you ain't thai, so thus ends the discussion about the cost..

    Believe me if ANYONE who is even remotely friends with your thai significant other did anything on this project it was for the "white buffalo price", or "special price for you"..

    I've found the less thaiz know someone in construction projects; the more likely they are to be able to keep the standards (low as they are here) to something that're workable and keep the price in line with the bid..

    Still, good luck with it..
    "Whoever said `Money can`t buy you love or joy` obviously was not making enough money." <- quote by Gene $immon$ of the rock group KISS

  25. #25
    Member
    Hoops's Avatar
    Join Date
    Sep 2014
    Last Online
    06-02-2015 @ 05:48 AM
    Posts
    69
    Quote Originally Posted by toddaniels View Post
    All I can say is that is one fucking expensive shed!!! Especially for one which appears to be between Nakhon Nowhere and "where-the-fuck-are-we" Thailand!

    There isn't a thai in this country who'd fork out that kinda dosh for what the pix show..

    Then again, you ain't thai, so thus ends the discussion about the cost..

    Believe me if ANYONE who is even remotely friends with your thai significant other did anything on this project it was for the "white buffalo price", or "special price for you"..

    I've found the less thaiz know someone in construction projects; the more likely they are to be able to keep the standards (low as they are here) to something that're workable and keep the price in line with the bid..

    Still, good luck with it..
    Well there is always some Thai willing to put some extra cream on top of the pudding for sure, but I checked the Toa price against Global House and Thai Watsuda and TOA was cheaper. We haven't spent all the 350k baht yet. The electrical installation has to be done, the roller doors, the gutters.

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •