    Payment schedule for building a house

    I know that this may be difficult to answer, but I'm wondering how it works paying for a build. Is it a lump sum upon signing contract and then payments made for specific work done at certain contractual intervals? I know that this is all relative to the building company, the budget etc. but I'm curious about ball park figures. stevefarang, DrAndy and Bettyboo are 3 people I'm curious about. My budget is around 3 million Baht. After initial signing for instance, do you pay like 20,000 at a time? And when? I truly don't know, so any insight would be helpful.

  2. #2
    Member

    Join Date
    May 2012
    Last Online
    18-03-2015 @ 11:59 PM
    Location
    Fla and Issan
    Posts
    199
    usually at "milestones" durring the build, and a sizeable last payment when you
    are happy will the final fit and finish

  3. #3
    Thailand Expat
    DrAndy's Avatar
    Join Date
    Nov 2005
    Last Online
    25-03-2014 @ 05:29 PM
    Location
    yes
    Posts
    32,025
    It is up to you and the builder to agree on a payment schedule

    That would depend on who is buying the materials, as he would need more in advance

    Just ask him to give you what he thinks should be paid and when and see if it seems reasonable

    For each of my builds I have had quite different schedules
    I have reported your post

  4. #4
    Lord of Swine
    Necron99's Avatar
    Join Date
    Feb 2012
    Last Online
    @
    Location
    Nahkon Sawon
    Posts
    13,021
    A reasonable schedule that gets everyone moving is deposit, then slab and structural, then walls, then roof, then lockup.

  5. #5
    Banned

    Join Date
    Oct 2008
    Last Online
    03-06-2014 @ 09:01 PM
    Posts
    27,545
    Quote Originally Posted by DrAndy View Post
    It is up to you and the builder to agree on a payment schedule

    That would depend on who is buying the materials, as he would need more in advance

    Just ask him to give you what he thinks should be paid and when and see if it seems reasonable

    For each of my builds I have had quite different schedules
    What Andy said.
    Difficult to pull a standard on this shite, as every situation will be different from the next.

    More likely to set a time frame for the build, pay some upfront......and than pay as you go. Contract or not. Best to be cautious in Thailand, yet not paranoid.

  6. #6
    Member
    stevefarang's Avatar
    Join Date
    Nov 2011
    Last Online
    06-07-2017 @ 01:57 AM
    Location
    Seattle, WA, USA
    Posts
    935
    We're paying in stages. Each stage has certain things to be accomplished.

    Be sure to include a damages clause if they fail to meet the schedule. For instance, we signed an extension of 200 days last August. Every day beyond that costs them XXX baht.

  7. #7
    Member
    Koetjeka's Avatar
    Join Date
    Aug 2012
    Last Online
    12-11-2015 @ 02:07 AM
    Location
    Chomphra (Surin province)
    Posts
    462
    Always pay at milestones and take an engineer with you to check everything before handing over the money! Milestones you might want to use:
    -foundation
    -ground floor/2nd floor, etc
    -roof (in the Netherlands we use the term "wind and waterproof")
    -kitchen
    -finishings
    -garden

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •